Dominion Energy has disclosed a roughly 9% increase in the cost of the 176-turbine Coastal Virginia Offshore Wind (CVOW) project.
The 2.6GW development, which has received full permits, is now about 50% complete and remains scheduled for completion by the end of 2026.
Despite this progress, the estimated total project costs—including contingency but excluding financing—have risen from $9.8bn to $10.7bn.
This marks the first cost increase since the original budget was submitted to the Virginia State Corporation Commission (SCC) in November 2021.
The rise in costs is primarily due to higher network upgrade expenses, which PJM, the regional grid operator, has assigned to CVOW as part of the generator interconnection process, as well as increased onshore electrical interconnection costs.
Projects built within PJM’s jurisdiction, such as CVOW, are allocated costs deemed necessary to integrate them effectively and maintain grid reliability.
While onshore expenses have increased, overall costs for other project components, including offshore elements, have remained aligned with the original budget.
Dominion Energy has emphasised that the project incorporates strong cost-sharing mechanisms to safeguard both customers and stakeholders.
Following a stakeholder settlement approved by the SCC in December 2022, 50% of any costs exceeding $10.3bn cannot be passed on to customers and must instead be absorbed by the project owners.
With the latest cost adjustments, Dominion Energy has estimated that the typical residential customer using 1,000kWh per month will see an average bill increase of 43 cents per month over the lifetime of the project.
Beyond cost-sharing measures for customers, Dominion Energy also has a non-controlling equity financing arrangement with Stonepeak.
Under this agreement, Stonepeak will contribute approximately $450m—half of the estimated $900m cost increase.
Dominion Energy has also reported that CVOW continues to achieve “significant construction milestones,” including the installation of the first 16 transition pieces, which connect each of the 176 wind turbines’ foundations to their towers.
Additionally, the first of three 4,300-tonne offshore substations was delivered to the Portsmouth Marine Terminal in Virginia Beach at the end of January.
Meanwhile, wind turbine tower and blade fabrication is in progress, with nacelle manufacturing set to commence later this quarter.
We are a leading global infrastructure and renewables search & recruitment business. Don’t forget to follow us on LinkedIn to keep up to date on our opportunities and current news. Please get in contact to discuss your hiring needs, salary bench-marking or market information: info@infra-be.com.
Join us on our podcast and subscribe to our newsletter to embark on an enlightening journey through the exciting landscapes of infrastructure and renewable energy. Stay connected, stay informed, and be part of the InfraBe community.
Tune in to our engaging podcast series where we dive deep into the dynamic realm of infrastructure and renewable energy. Join us as we discuss industry trends, innovative technologies, sustainable practices, and insightful interviews with experts and thought leaders. Stay informed and inspired on the go, gaining valuable insights to shape your perspective on the ever-evolving landscape of global infrastructure and renewables.