Ørsted has decided to halt development of its 2400MW Hornsea 4 offshore wind farm, located off the east coast of England, due to mounting supply chain costs, rising interest rates, and growing challenges around project execution.
Although the project secured a UK Contract for Difference (CfD) in September 2024, the Danish energy firm confirmed it will not move forward in its current form.
“Since the award, the project has seen several adverse developments relating to continued increase of supply chain costs, higher interest rates, and an increase in the risk to construct and operate Hornsea 4 on the planned timeline for a project of this scale,” the company stated.
“In combination, these developments have deteriorated the value creation of the project and increased the execution risk.”
In a statement alongside Ørsted’s first-quarter results, chief executive Rasmus Errboe reiterated: “The combination of increased supply chain costs, higher interest rates, and increased execution risk have deteriorated the expected value creation of the project.”
He continued, “We remain fully committed to being an important partner to the UK government to help them achieve their ambitious target for offshore wind build-out and appreciate the work they’ve done to deliver a clear framework to support offshore wind.
“However, our capital allocation is based on a strict and value-focused approach, and after careful consideration, we’ve decided to discontinue the development of the Hornsea 4 project in its current form, well ahead of the planned Final Investment Decision later this year.”
Errboe explained that Ørsted had spent the last nine months progressing the project and engaging closely with suppliers and stakeholders to address risks associated with a development of this magnitude.
“Throughout the development phase we’ve been very diligent in our approach to capital commitment to our suppliers, and our committed capital is well below our threshold. The adverse macroeconomic developments, continued supply chain challenges, and increased execution, market and operational risks have eroded the value creation.”
Despite this setback, Errboe affirmed Ørsted’s confidence in the long-term potential of the UK offshore wind sector: “I’d like to emphasise that Ørsted continues to firmly believe in the long-term fundamentals of and value perspectives for offshore wind in the UK. We’ll keep the project rights for the Hornsea 4 project in our development portfolio, and we’ll seek to develop the project later in a way that is more value-creating for us and our shareholders.”
The move aligns with Ørsted’s updated capital allocation framework and stage gate approach, which focus on making early decisions to prevent escalating break costs.
As a result of the cancellation, the company anticipates an EBITDA impact of Dkr3.0–3.5 billion (up to €470 million) in the second quarter of 2025. This includes write-downs related to offshore transmission assets and provisions for contract termination costs.
An additional impairment of Dkr0.5–1.0 billion is expected for capitalised construction expenses.
Hornsea 4 had been planned as the next development in Ørsted’s major Hornsea cluster off England’s east coast.
Elsewhere in its results, Ørsted reported first-quarter EBITDA of Dkr8.9 billion, an increase from Dkr7.5 billion in the same quarter of the previous year.
Offshore wind operations contributed Dkr7.7 billion (€1.2 billion) to this total, representing a Dkr700 million year-on-year rise. This growth was mainly driven by the ramp-up of its Gode Wind 3 offshore wind farm in Germany and improved operational availability, though it was partly offset by lower wind speeds during the quarter.
Errboe commented, “I’m pleased with our operational performance and earnings in Q1 2025, and we remain fully focused on the execution of our four strategic priorities.
“During the quarter, we had solid operational earnings supporting our full-year guidance, and we continued to deliver on our farm-down programme by completing offshore and onshore farm-downs. We also continued to deliver on our construction portfolio as we commissioned our offshore wind farm Gode Wind 3 in Germany, reaching more than 10 GW of installed offshore capacity.”
We are a leading global infrastructure and renewables search & recruitment business. Don’t forget to follow us on LinkedIn to keep up to date on our opportunities and current news. Please get in contact to discuss your hiring needs, salary bench-marking or market information: info@infra-be.com.
Join us on our podcast and subscribe to our newsletter to embark on an enlightening journey through the exciting landscapes of infrastructure and renewable energy. Stay connected, stay informed, and be part of the InfraBe community.
Tune in to our engaging podcast series where we dive deep into the dynamic realm of infrastructure and renewable energy. Join us as we discuss industry trends, innovative technologies, sustainable practices, and insightful interviews with experts and thought leaders. Stay informed and inspired on the go, gaining valuable insights to shape your perspective on the ever-evolving landscape of global infrastructure and renewables.