Welcome to Infra-Be! We are a top-tier global infrastructure and renewable energy search & recruitment firm. Whether you’re seeking the best talent, salary benchmarking, or market insights, we’re here to help. Reach out to us at info@infra-be.com or click here to get in touch.
Orlen and Northland Power have begun construction on Poland’s first offshore wind farm, the 1200MW Baltic Power.
Following extensive preparations, a fleet of 11 specialised vessels has been deployed to install the project’s foundations.
The installation phase has already seen the successful placement of the first two of 78 monopiles—100-metre steel structures designed to support 15MW wind turbines.
The 1.2GW Baltic Power wind farm is scheduled to begin operations in 2026.
Offshore wind plays a crucial role in the ORLEN Group’s new strategy, which aims to establish over 4GW of installed capacity in the Baltic Sea through partnerships with key industry leaders.
As the first and most advanced offshore wind energy project in the Polish Baltic Sea, Baltic Power marks a significant step in Poland’s renewable energy transition.
Orlen has also committed to expanding its offshore wind portfolio by developing three additional wind farms, for which it has already secured licences.
Offshore wind, alongside large-scale energy storage, onshore renewables, gas-fired power plants, and small modular reactors, will form a key pillar of Poland’s evolving energy landscape.
“Our new strategy is about action and delivering tangible progress, as demonstrated by Poland’s first offshore wind farm.”
“After months of intensive work, we are proud to confirm that the first foundations for the Baltic Power project have been installed.”
“By 2026, energy from the Baltic Sea will be flowing to consumers for the first time. This is clean, stable, and secure power that will drive Poland’s economy forward.”
“It also creates opportunities for Polish businesses to grow alongside our project. This is the energy of tomorrow – starting today,” said Ireneusz Fafara, President of the Management Board and CEO of Orlen.”
Orlen is committed to maximising Polish industry involvement throughout the entire 30-year lifespan of the Baltic Power wind farm.
Key components, such as turbine nacelles, subsea cables, offshore substation steel structures, and foundation elements, are being manufactured in Szczecin, Bydgoszcz, the Tri-City area, Zary, and Niemodlin.
Additionally, Polish companies are contributing through geological surveys, engineering design, and logistics support.
“As co-developers of Poland’s first offshore wind farm, we are excited to contribute our global experience in offshore wind projects.”
“This achievement not only demonstrates our progress together, but also fuels our determination.”
“Safety remains our top priority throughout every stage, ensuring we uphold the highest standards in every aspect of the project. Today’s milestone is a testament to the strong partnership between Northland and ORLEN and further solidifies our shared commitment to Poland’s energy future,” said Christine Healy, President and CEO of Northland Power.
Beyond the crane vessel, more than ten specialised ships are actively involved in construction, including support vessels, tugboats, personnel and equipment carriers, environmental monitoring vessels, and security patrols.
The Baltic Power Offshore Coordination Centre is responsible for overseeing all offshore construction activities and maritime traffic in real time.