The body responsible for planning Britain’s future energy system has confirmed a new priority list of projects to be connected to the electricity network, marking one of the most significant reforms to grid access in decades.
The National Energy System Operator (NESO) said its revised approach is designed to break the long backlog of stalled schemes, unlock billions of pounds in private investment and support the government’s ambition to deliver a fully decarbonised power system by 2030.
A New Approach to Grid Connections
For years, Britain has operated a first-come, first-served queue for electricity network access. That structure left thousands of schemes waiting for connection slots, creating a decade-long bottleneck and allowing so-called “zombie projects” to clog the system. At its peak, more than 700GW of generation and storage capacity was sitting in the queue — several times more than required for the 2030 clean-power objective.
NESO’s new process instead prioritises schemes that are aligned with national energy targets and ready to build, such as those that already hold planning permission or land rights. Around 3,000 applications have been assessed under the redesigned system.
The operator said it will begin informing developers from today whether they have been placed in the initial priority pipeline. Projects that do not secure a place may reapply during future windows or if further capacity becomes available, provided they can demonstrate readiness and policy alignment.
Scale of the Pipeline
According to NESO, 132GW of projects have been identified as essential to meeting the UK government’s 2030 goals, while a further 151GW are expected to be required by 2035. Almost 100GW of new or expanded transmission demand connections also form part of the updated pipeline.
NESO argues the reforms could unlock as much as £40bn of annual investment by accelerating viable schemes and signalling clarity to investors. The work has been developed in collaboration with the UK, Scottish and Welsh governments, Ofgem, network operators and industry representatives.
Kayte O’Neill, Chief Operating Officer at NESO, said “Transforming the grid connections process is a vital first step in unlocking the capacity needs for a secure, affordable energy transition. These changes will cut grid bottlenecks by prioritising ready-to-build projects, giving certainty about when and where they can connect and unlocking billions in clean energy investment.
“These changes wouldn’t be possible without the collaboration of our partners over the last two years. Together, we’re laying the foundations for a resilient, efficient and future-ready energy system that delivers for British consumers and the economy.”
Government and Regulator Welcome the Shift
Ministers have positioned the connection backlog as a key barrier to national energy security and economic growth. The Energy Secretary, Ed Miliband, said “We inherited a broken system where zombie projects were allowed to hold up grid connections for viable projects that will bring investment, jobs and economic growth. To fix this we embarked on ambitious, once in a generation reforms to clean up the queue and prioritise the projects that are ready to help us deliver clean power by 2030. Every solar farm, wind farm or battery storage facility we connect to the electricity grid brings us closer to clean, homegrown, power that we control – so we can get bills down for good.”
Regulator Ofgem — which has argued that rapid growth in technologies such as EVs, heat pumps and data centres is reshaping Britain’s energy needs — also backed the new prioritisation.
Jonathan Brearley, CEO of Ofgem, said “We are embarking on the biggest transition our energy system has ever undergone. The destination is clear: a more stable electricity system, a system that is secure, and a system that is ultimately affordable for customers. The way we use energy is evolving. From AI-driven technologies and power-hungry data centres to the surge of electric vehicles on our roads and heat pumps in our homes, demand has reached unprecedented levels.
“Together we’ve cleared the gridlock and created a new pipeline that prioritises the projects Britain needs most. We are building grids as fast as the sector possibly can, while ensuring generation gets connected. Every step is focused on delivering real value for customers and creating an energy system that works for the future.”
Industry Reaction: Reform Seen as “Pivotal”
Industry bodies have repeatedly warned that delays in connecting new projects risk undermining Britain’s clean-energy leadership. The announcement was broadly welcomed across the sector, with many viewing it as a turning point.
Chris Stark, Head of Mission Control for Clean Power 2030, said “Queuing is a very British tradition, but the queue to connect to Britain’s grid has held back our economy. This overhaul of the connections process is the single most important step we will take towards a clean power system. The energy projects our country needs now have the green light to deploy at a pace we haven’t seen for decades. This unlocks the modern, clean energy system Britain needs for 2030 and beyond.”
Clare Jackson, CEO of Hydrogen UK, said “We are pleased to see the results of NESO’s Connections Reform. Hydrogen has an important role in the UK’s Clean Power ambitions, supporting energy demand while driving industrial decarbonisation. The results open the door and free up space for further hydrogen innovation and accelerated project development. Hydrogen’s standout advantage is its ability to store energy at scale, providing the flexibility and reliability needed to deliver power on demand and strengthen the resilience of our future energy system.”
Dhara Vyas, CEO of Energy UK, said “A stable, secure energy system depends on ensuring that we can connect more clean power generation to our grid in the coming years. Addressing the issues in the connections queue is critically important and today marks an important milestone with the announcement of a new project pipeline that will unlock investment across the country. The National Energy System Operator, Government, and the regulator have worked closely with industry to transform the connections process, and this reform is just the beginning. The energy industry is keen to see planning and environmental processes further streamlined to ensure projects and infrastructure are built out efficiently across the country. Continued efforts will drive investment and create jobs in communities throughout Great Britain, reduce our reliance on volatile gas prices and, ultimately, lead to stable, affordable energy bills for households and businesses.”
Lawrence Slade, Chief Executive of ENA, said “This announcement from NESO marks a pivotal moment for the energy sector as a whole. The complex task of reforming the connections queue has required deep collaboration across the sector. Networks have played a critical role by working closely with customers and industry, conducting detailed evidence checks and providing timely submissions to NESO. Ultimately, this reformed connections process will mean fair and faster connections for GB customers.”
Shevaun Haviland, Director General of the British Chambers of Commerce, said “For too long, businesses have been impacted by lengthy queues to get connected to the grid, holding firms back as they look to expand or decarbonise. NESO’s reforms to the grid will be enthusiastically welcomed by businesses. It is now critical that they lead to real-world delivery. Ensuring quicker connections to the grid and cutting queues are desperately needed so businesses can support economic growth across the UK.”
Who are InfraBe?
We are a leading global infrastructure and renewables search & recruitment business. Don’t forget to follow us on LinkedIn to keep up to date on our opportunities and current news. Please get in contact to discuss your hiring needs, salary bench-marking or market information: info@infra-be.com.
Join us on our podcast and subscribe to our newsletter to embark on an enlightening journey through the exciting landscapes of infrastructure and renewable energy. Stay connected, stay informed, and be part of the InfraBe community.
Tune in to our engaging podcast series where we dive deep into the dynamic realm of infrastructure and renewable energy. Join us as we discuss industry trends, innovative technologies, sustainable practices, and insightful interviews with experts and thought leaders. Stay informed and inspired on the go, gaining valuable insights to shape your perspective on the ever-evolving landscape of global infrastructure and renewables.