Denmark’s transmission operator Energinet plans to abandon its long-standing first-come-first-served procedure for connecting new energy projects to the high-voltage grid, introducing a fundamentally different model from early 2026. The shift is designed to move the most advanced solar, wind, battery and major power-using facilities through the queue faster at a time when demand for grid access has surged.
New Prioritisation Framework
The company aims to replace what it describes as an increasingly unworkable allocation process with one that rewards readiness. Developers will no longer be able to secure a place in the screening line simply by being early applicants; instead, they must demonstrate that their projects have reached a defined level of maturity. This includes evidence that land can be secured and that a credible timetable has been established for local planning and environmental approvals.
Kim Willerslev Jakobsen, Energinet’s director for system responsibility, said “The first-come-first-served principle is no longer beneficial, neither for the green transition nor for the plant owners.”
Advancing Projects That Can Use Existing Capacity
Once screened, eligible developments will be sorted into ranked groups according to how effectively they can utilise current grid infrastructure and whether their local municipality has already advanced a relevant planning proposal. Projects that demand minimal reinforcement work, or that have progressed furthest through local authority procedures, will be allowed to move ahead sooner than less developed schemes.
Energinet said the new structure is intended to relieve mounting screening and permitting delays, which have expanded as both renewable developers and major electricity consumers seek to connect to Denmark’s transmission network. The organisation argues that prioritising maturity will help reduce bottlenecks, accelerate investments and support the country’s wider decarbonisation trajectory.
Consultation and Further Measures
Stakeholders are invited to comment on the revised approach until 1 January. The operator intends to bring the model into force on 1 February 2026. It emphasised that this marks the beginning of a broader programme aimed at streamlining the journey to grid connection, while expansion projects initiated by distribution system operators will continue unaffected.
About Energinet
Energinet is Denmark’s state-owned transmission system operator, responsible for the secure and efficient operation of the country’s electricity and gas networks. The organisation plays a central role in integrating renewable energy, planning grid expansion and maintaining system reliability as Denmark advances towards a climate-neutral energy system. More information is available at
Who are InfraBe?
We are a leading global infrastructure and renewables search & recruitment business. Don’t forget to follow us on LinkedIn to keep up to date on our opportunities and current news. Please get in contact to discuss your hiring needs, salary bench-marking or market information: info@infra-be.com.
Join us on our podcast and subscribe to our newsletter to embark on an enlightening journey through the exciting landscapes of infrastructure and renewable energy. Stay connected, stay informed, and be part of the InfraBe community.
Tune in to our engaging podcast series where we dive deep into the dynamic realm of infrastructure and renewable energy. Join us as we discuss industry trends, innovative technologies, sustainable practices, and insightful interviews with experts and thought leaders. Stay informed and inspired on the go, gaining valuable insights to shape your perspective on the ever-evolving landscape of global infrastructure and renewables.